Skip to Main Content

Al Harris Library Renovations: Gallery

Evolution of the Library's Renovation Project on the Second Floor

periodical deselection back wall

Deselection and Recycling of Print Periodicals (May 3, 2019)

Due to access with electronic resources, select print periodical titles were deselected from the library's holdings and the paper was recycled. View of stacked periodicals along the back west wall, first floor.

periodical deselection back stairwell

Deselection and Recycling of Print Periodicals (May 3, 2019)

VIew of stacked periodicals to be recycled along the back staircase, first floor.

periodical deselection public services office

Deselection and Recycling of Print Periodicals (May 3, 2019)

View of stacked periodicals to be recycled in the Public Services Office, first floor.

juvenile collection

Relocation of the Juvenile Collection (May 3, 2019)

Juvenile Collection moved from second floor to the first floor, preceding the periodicals collection.

group study room 1

Group Study Room #1 (May 13, 2019)

Removed chairs and tables.

group study room 3

Group Study Room #3 (May 13, 2019)

Removed chairs and tables.

huddle room

Huddle Room (May 13, 2019)

Removed chairs and one table.

second floor furniture removal

Second Floor, Study Area Adjacent to Back Staircase (May 13, 2019)

Removed study carrels, tables and chairs.

second floor furniture removal

Second Floor, Northwest Corner (May 13, 2019)

Removed study carrels, tables, chairs and dry erase boards.

second floor furniture removal

Second Floor, Southwest Corner (May 13, 2019)

Removed study carrels, tables, chairs and dry erase boards. 

second floor furniture removal

Second Floor, Southeast Corner (May 13, 2019)

Removed study carrels, tables, chairs, dry erase boards, and atlas cases.

southwestern room removal of collections

Southwestern Room (May 13, 2019)

Process of removing collections and other materials from the Southwestern Room.

southwestern room furniture removal

Southwestern Room (May 30, 2019)

Removed all collections, archival cabinets, and chairs.

juvenile and curriculum collections

Relocation of Juvenile and Curriculum Collections (May 30, 2019)

The complete relocation of the Juvenile and Curriculum collections to the first floor.

periodicals removed

Deselected Periodicals Removed (May 30, 2019)

All deselected periodicals have been collected and removed. Seating areas restored to their prior condition.

instruction room north side

Instruction Room (May 30, 2019)

Removed computer equipment, chairs, instructor podium, and printer. Remaining furniture was moved to north side of the room.

instruction room south side

Instruction Room (May 30, 2019)

Shelving aisle end caps placed in south side of the Instruction Room.

second floor emptied

Second Floor, View from Southwest Corner (May 30, 2019)

Looking along the study carrel rooms, this vantage point from the southwest corner shows over half the books and shelving aisles removed.

second floor emptied

Second Floor, a Diagonal View from Southwest Corner (May 30, 2019)

Looking diagonally across the floor from the southwest corner, shows the emptied second floor from east to west.

second floor emptied

Second Floor (May 30, 2019)

Process of removing the book collection and dismantling the shelving.

loading dock

Library Loading Dock (May 30, 2019)

Full book trucks awaiting to be transported offsite.

loading book trucks

Library Loading Dock (May 30, 2019)

Loading transport trailer with book trucks.

unloading trailer

Unloading Transport Trailer at Offsite Facility (May 30, 2019)

Unloading transport trailer at offsite storage facility.

offsite storage

Offsite Storage Facility (May 30, 2019)

Library's book collection placement at offsite storage facility.

offsite storage

Offsite Storage Facility (May 30, 2019)

Library's second floor shelving being reassembled at offsite storage facility.

instruction room

Instruction Room (June 3, 2019)

Moved display cabinets and wood shelves from Southwestern Room into the Instruction Room.

southwestern room

Southwestern Room (June 3, 2019)

Removed all remaining furniture from room.

second floor

Second Floor (June 3, 2019)

Dismantling all excess shelving.

microform area

First Floor, Southwest Corner (June 3, 2019)

Placement of excess shelving and furniture from second floor.

excess shelving

First Floor, Southwest Corner (June 7, 2019)

Placement of excess shelving (unused shelving at offsite storage facility)

abatement seal

Back Stairwell (June 11, 2019)

Back stairwell sealed off during the abatement process on the second floor.

back stairwell

Back Stairwell (June 11, 2019)

All stairwells blocked off to the public.

back stairwell

Second Floor, Back Stairwell Area (July 3, 2019)

Concrete floor after abatement of second floor completed

northeast corner floor

Second Floor, Northeast Corner (July 3, 2019)

Concrete floor after abatement of second floor completed. Dark area is where the floor was patched at the cold joint.

northeast corner floor

Second Floor, Northeast Corner (July 3, 2019)

Concrete floor after abatement of second floor completed.

second floor window area

Second Floor, Eastside & Windows (July 3, 2019)

Concrete floor after abatement of second floor completed.

second floor facing east

Second Floor, Facing East (July 3, 2019)

Concrete floor after abatement of the second floor completed. Dark area is where the floor was patched at the cold joint.

second floor facing south

Second Floor, Facing South (July 3, 2019)

Concrete floor after abatement of the second floor completed. Dark area is where the floor was patched at the cold joint.

second floor facing southwest

Second Floor, Facing Southwest (July 3, 2019)

Concrete floor after abatement of the second floor completed. Dark area is where the floor was patched at the cold joint.

group study room three

Group Study Room #3 (July 3, 2019)

Concrete floor after abatement of the second floor completed.

southwestern room

Southwestern Room (July 3, 2019)

Concrete floor after abatement of the second floor completed.

demolition of study carrels

Second Floor, Study Carrels (July 5, 2019)

Demolition of the exterior walls of the study carrels.

demolition of study carrels

Second Floor, Study Carrels (July 5, 2019)

Demolition of the exterior walls of the study carrels.

demolition of study carrels

Second Floor, Study Carrels (July 5, 2019)

Demolition of the exterior walls of the study carrels.

west wall

Second Floor, West Wall (July 12, 2019)

View of the west wall after the completed removal of all study carrel rooms.

wood paneling removed

Instruction Room (July 12, 2019)

Wood paneling removed from north walls.

wood paneling removed

Group Study Room #1

Wood paneling removed from north walls.

wood paneling removed

Group Study Room #3 (July 12, 2019)

Wood paneling removed from north walls.

wood paneling removed

Hallway to Southwestern Room (July 12, 2019)

Wood paneling removed from north walls.

group study room three

Group Study Room #3 (July 19, 2019)

Demolition of Group Study Room #3, view of the back wall.

group study room three

Group Study Room #3 (July 19, 2019)

Demolition of Group Study Room #3, view of the side wall.

group study room three

Group Study Room #3 (July 19, 2019)

Demolition of Group Study Room #3, view from door/hallway.

back stairwell

Back Stairwell (July 25, 2019)

Concrete steps after abatement of the stairwell (completed after the floor).

south stairwell

South Stairwell (July 25, 2019)

Concrete steps after abatement of the stairwell (completed after the floor).

southwestern room

Southwestern Room (July 25, 2019)

Demolition of the Southwestern Room, view of the back wall.

southwestern room and group study room three

Southwestern Room and Group Study Room #3 (July 25, 2019)

Demolition of the Southwestern Room and Group Study Room #3.

Ethernet wire rack

Ethernet Wire Rack (September 3, 2019)

Installation of the wire rack for the Ethernet upgrades for the entire building.

removal of ceiling tiles

Second Floor, Ceiling Along West Wall (September 3, 2019)

Removal of ceiling tiles, moving from west to east.

stacked ceiling tiles

Second Floor, Southeast Corner (September 3, 2019)

Removed ceiling tiles are stacked along the wall in the southeast corner of the second floor.

stacked ceiling tiles

Second Floor, Southeast Corner (October 16, 2019)

Removed ceiling tiles are stacked along the wall in the southeast corner of the second floor.

stacked ceiling tiles

Second Floor, Southeast Corner (October 16, 2019)

Removed ceiling tiles are stacked along the walls in the southeast corner of the second floor.

Ethernet wire rack

Ethernet Wire Rack (October 16, 2019)

Installation of new Ethernet wiring for the building.

ceiling grid removal

Second Floor, Ceiling Along Southwest Corner (October 16, 2019)

Removal of ceiling grid in the southwest corner.

ceiling grid removal

Second Floor, Ceiling Along Southwest Corner (October 16, 2019)

Removal of ceiling grid in the southwest corner.

ceiling grid removal

Second Floor, Ceiling Along Northwest Corner (October 16, 2019)

Removal of ceiling grid in the northwest corner.

ceiling grid removal

Second Floor, Ceiling Along Northwest Corner (October 16, 2019)

Removal of ceiling grid in the northwest corner.

ceiling grid removal

Second Floor, Ceiling Around Northwest Corner and Outside Instruction Room (October 16, 2019)

Removal of ceiling grid in the northwest corner and outside of the Instruction Room.

ceiling grid removal

Second Floor, Mid-floor Ceiling (November 1, 2019)

Removal of ceiling grid in the middle of the second floor.

light fixture removal

Second Floor, North-side Ceiling (November 1, 2019)

Removal of the majority of light fixtures from the north side of the second floor.

removal of ventilation ducts

Second Floor, North-side Ceiling (November 1, 2019)

Removal of the older ventilation ducts from the north side of the second floor.

second floor ceiling

Second Floor, Mid-floor Ceiling (November 11, 2019)

Removal of majority of older ceiling components completed.

second floor ceiling

Second Floor, Southeast Corner Ceiling (November 11, 2019)

Removal of majority of older ceiling components completed. With most light fixtures removed, sections of the second floor are quite dark.

second floor ceiling

Second Floor, Southwest Corner Ceiling (November 11, 2019)

Removal of majority of older ceiling components completed. With most light fixtures removed, sections of the second floor are quite dark.

second floor ceiling

Second Floor, Northwest Corner Ceiling (November 11, 2019)

Removal of majority of older ceiling components completed.

removal of ceiling tiles

Second Floor, Southeast Corner (November 12, 2019)

Removal of stacked ceiling tiles.

ceiling tiles on loading dock

Loading Dock, Removal of Ceiling Tiles (November 11, 2019)

Removal of second floor ceiling tiles.

disposal of ceiling tiles

Loading Dock, Disposal of Ceiling Tiles (November 11, 2019)

Flatbed truck used to dispose of ceiling tiles and other pieces of debris.

closed back stairwell

Second Floor, Closure of Back Stairwell (January 13, 2020)

Back stairwell was closed to allow for a large flat surface to read the architectural drawings during construction.

removal of wood paneling outside instruction room

Second Floor, Removal of Wood Paneling Outside Instruction Room (January 13, 2020)

Removal of the wood paneling on the walls adjacent to the Instruction Room.

wall frame for exterior wall of archive storage vault

Second Floor, Northwest Corner (January 13, 2020)

View of the northwest corner, placement of new wall frames for the exterior wall of the new archive's storage vault.

drop ceiling framing on northside

Second Floor, Ceiling on North Side (January 13, 2020)

Placement of the new ceiling frames for drop ceiling accents along the north side and in front of the new archive.

wall and ceiling framework looking toward northwest corner

Second Floor, Northwest Corner (January 13, 2020)

View of northwest corner from south side, placement of new wall and ceiling framework.

new ductwork

Second Floor, New Ductwork (January 13, 2020)

View of the new ductwork placed throughout the second floor ceiling. Additionally, you can see the different stages of completion on the framing of the drop ceiling accent pieces.

drop ceiling framing around lightboxes

Second Floor, Drop Ceiling Framework Around Lightboxes (January 13, 2020)

View of the square ceiling framework for the new LED lightboxes.

wall framing for new study spaces

Second Floor, Southwest Corner (January 13, 2020)

Placement of new wall frames for the new study spaces in the southwest corner.

wall framing for custodial room extension

Second Floor, Southwest Corner (January 17, 2020)

View of the wall frame enclosure for the custodial room extension.

ladder access to roof

Second Floor, Roof Access (January 17, 2020)

With the upstairs custodial closet cleared out for renovation, it allows for the opportunity to take a photo of the ladder access to the roof of the library. One of those hidden gems of the building's structure.

new ductwork

Second Floor, Southwest Corner (January 17, 2020)

View of new ductwork and other supplies for installation in the southwest corner.

drywall installation

Second Floor, Drop Ceiling Drywall Installation (January 17, 2020)

Placement of drywall to fit drop ceiling accents.

drywall installation

Second Floor, Drop Ceiling Drywall Installation (January 17, 2020)

Placement of drywall to fit drop ceiling accents on south side of the floor.

loading dock filled with ductwork, supplies and tools

Basement, Loading Dock Area (January 17, 2020)

At the height of construction, the loading dock area was congested with pieces of ductwork, supplies, furniture, and tools allowing a narrow walking path to the elevator, auditorium and Writing Center. 

discarded old ductwork

Loading Dock, Removal of Old Ductwork (January 17, 2020)

Removal of old ductwork from second floor

expansion ceiling cover

Second Floor, Expansion Ceiling Cover (January 24, 2020)

With the drop ceiling removed, it allows for the opportunity to take a photo of an expansion ceiling cover verifying the rumor that this building was constructed to accommodate a third floor. This sheet metal expansion covers a natural void to allow for the construction of a new stairwell extension to a potential third floor.

removal of wood slats

Second Floor, Removal of Wood Slats (January 24, 2020)

Removal of vertical wood slats along the walls adjacent to the elevator and south side restrooms.

electrical work on upstairs breaker boxes

Second Floor, Electrical Work (January 24, 2020)

As part of the construction, the electrical wiring needed to be brought up to current building code. This shows the breaker box housing removed and the work in progress.

new ductwork

Second Floor, Southwest Corner (January 24, 2020)

View of new ductwork in the southwest corner.

new ductwork

Second Floor, South Wall (January 24, 2020)

View of new ductwork along the south wall.

new ductwork supplies

Second Floor, West Wall (January 24, 2020)

View of new ductwork supplies stacked along the west wall and behind the back stairwell.

new ductwork

Second Floor, Mid-floor (January 24, 2020)

View of new ductwork components to split the airflow across the area.

new ductwork

Second Floor, Southeast Corner (January 24, 2020)

Close-up view of new ductwork components to split the airflow across the area.

electrical box on ductwork

Second Floor, West Wall (January 24, 2020)

Close-up view of the electrical box attached to the new ductwork.

ceiling removal

Second Floor, North Hallway (January 24, 2020)

Removal of drop ceiling tiles and grid in the north hallway.

drywall installation

Second Floor, Walls Around Northeast Corner and Outside Instruction Room (January 24, 2020)

View of drywall installation along the walls adjacent to the Instruction Room.

drywall installation

Second Floor, North Side (January 24, 2020)

View of the drywall installation of the drop ceiling accents in front of the restrooms on the north side of the floor.

drywall installation

Second Floor, Drop Ceiling Drywall Installation (January 24, 2020)

View of the drywall installation of the drop ceiling accents outside of the Instruction Room.

drywall installation

Second Floor, Columns (January 24, 2020)

Close-up view of the drywall installation atop of the columns.

drywall installation

Second Floor, Mid-floor (January 24, 2020)

View of the drywall installation of the drop ceiling accents at mid-floor.

drywall installation

Second Floor, South Side (January 24, 2020)

View of the drywall installation of the drop ceiling accents in front of the restrooms on the south side of the floor.

drywall installation

Second Floor, Exterior of Archive (January 24, 2020)

View of the drywall installation on the exterior wall of the archive storage vault.

frame for signage cutout

Second Floor, Exterior of Archive (January 24, 2020)

Close-up view of the framing of the signage cutout to eventually house pictures and biographical information of Tom Stafford.

wall frame for exterior wall of archive storage vault

Second Floor, Storage Vault (January 24, 2020)

Interior view of the exterior wall of the storage vault. Drywall installation applied to the exterior while the interior view shows the wall frame.

drywall installation

Second Floor, Exterior of Archive (January 24, 2020)

View of the drywall installation of the drop ceiling accents outside the south exterior wall of the storage vault.

drywall installation

Second Floor, Exterior of Archive (January 24, 2020)

View of the drywall installation in progress on the south exterior wall of the storage vault.

wall frame for exterior wall of archive storage vault

Second Floor, Exterior of Archive (January 24, 2020)

View of the wall frame for the remaining south exterior wall of the storage vault and the wall for the new utility room.

wall framing for new office

Second Floor, Office Space (January 24, 2020)

View of the wall frame for the new office space and utility room next to the storage vault.

wall frame for wall between vault and sorting room

Second Floor, Storage Vault (January 24, 2020)

View of the wall frame and doorways. Left side is the new sorting room (staff area) and the doorway on the right, leads to the new reading room (visitor area) for the archive.

wall frame of sorting room

Second Floor, Sorting Room (January 24, 2020)

VIew of the wall frame for the new sorting room (staff area) including a reverse view of the framed area of the storage vault.

wall frame for half wall of sorting room

Second Floor, Sorting Room (January 24, 2020)

Close-up view of wall frame for the sorting room's half wall.

drop ceiling framing in reading room

Second Floor, Reading Room (January 24, 2020)

View of the ceiling frames for the drop ceiling accents and lighting in the new reading room (visitor area).

drop ceiling framing mid-floor

Second Floor, Mid-floor (January 24, 2020)

View of the ceiling frames for the various drop ceiling accents throughout the center area of the second floor.

wall frame for custodial closet

Second Floor, Southwest Corner (January 24, 2020)

View of the wall frame for the custodial closet extension and the corner utility closet.

wall frames for study spaces

Second Floor, Southwest Corner (January 24, 2020)

View of the wall frames dividing the study spaces with the inclusion of electrical boxes and conduits. New ductwork elements placed within each space for placement.

drywall supplies

Second Floor, Southwest Corner (January 24, 2020)

View of drywall supplies placed for installation in the southwest corner.

second floor construction

Second Floor, Mid-floor (January 24, 2020)

Broad view looking north of the whole renovation process.

drywall installation

Second Floor, Southwest Corner (January 31, 2020)

Broad view of drywall installation for the southwest corner.

drywall installation

Second Floor, Southwest Corner (January 31, 2020)

View of drywall installation in progress on custodial closet extension and utility room.

drywall installation

Second Floor, Southwest Corner (January 31, 2020)

View of drywall installation in progress on study spaces along south wall. 

drywall installation

Second Floor, Southwest Corner (January 31, 2020)

View of drywall installation in progress on study spaces in southwest corner and along west wall.

construction on west wall

Second Floor, West Wall (January 31, 2020)

Broad view looking north of the whole renovation process along the west wall.

drop ceiling along on west wall

Second Floor, West Wall (January 31, 2020)

View of drywall installation and framing of drop ceiling along the west wall.

construction facing northwest

Second Floor, Mid-floor (January 31, 2020)

Broad view looking northwest of the whole renovation process.

wall insulation supplies

Second Floor, Mid-floor (January 31, 2020)

Placement of wall insulation supplies to complete wall construction in the archive area.

construction on east wall

Second Floor, East Wall (January 31, 2020)

Broad view looking northeast of the whole renovation process along the east wall.

new ductwork

Second Floor, Southeast Corner (January 31, 2020)

Placement of new ductwork and ductwork components in the southeast corner.

construction in southeast corner

Second Floor, Southeast Corner (January 31, 2020)

View of construction supplies placed in the southeast corner.

removal of water fountains

Second Floor, Water Fountains (January 31, 2020)

Removal of all water fountains from the second floor. 

new ductwork

Second Floor, Storage Vault (February 21, 2020)

Placement of new ductwork in the storage vault area. The ductwork in this area will operate independently from the rest of the second floor to maintain a climate-controlled environment.

drywall installation

Second Floor, Sorting Room (February 21, 2020)

Placement of drywall over insulation along the west wall of the Sorting Room.

placing insulation

Second Floor, Sorting Room (February 21, 2020)

Placement of insulation along the north wall of the Sorting Room and Reading Room.

construction in northwest corner

Second Floor, Reading Room (February 21, 2020)

Broad view looking northwest of the renovation work in the new archive.

drywall installation

Second Floor, Storage Vault (February 21, 2020)

Placement of drywall over insulation along the south wall of the storage vault.

drywall installation

Second Floor, Office Space (February 21, 2020)

Placement of drywall over insulation along the north and south walls of the new office space.

priming drywall

Second Floor, Exterior of Archive (February 21, 2020)

View of the drywall being primed for painting.

priming drywall

Second Floor, Southeast Corner (February 21, 2020)

View of the drywall being primed for painting in the southeast corner.

new ductwork

Second Floor, Huddle Room (February 21, 2020)

Removal of ceiling tiles to place new ductwork components in the Huddle Room and the adjacent Group Study Room #1.

sanding the floor

Second Floor, Mid-floor (February 21, 2020)

The process of removing any particles of mastic by sanding the floor and bagging the particles. By smoothing the floor's surface, it prepares the floor surface for a polished finish.

removal of mastic

North Stairwell (February 21, 2020)

View of the north stairwell looking down from second floor landing. Removal of any remaining particles of mastic by sanding the floor by hand.

removal of mastic

South Stairwell (February 21, 2020)

View of the south stairwell looking down from the second floor landing. Removal of any remaining particles of mastic by sanding the floor by hand.

removal of mastic

North Stairwell (February 21, 2020)

View of the shop-vac used to collect the dust and sanded particles from the stairwell landings.

concrete floors

South Stairwell (February 21, 2020)

View of second floor landing in the south stairwell after cleaning the floor from the sanding process.

construction in southeast corner

Second Floor, Southeast Corner (February 21, 2020)

Broad view of the construction process in the southeast corner.

construction in southeast corner

Second Floor, Southeast Corner (February 21, 2020)

Broad view of the construction process in the southeast corner looking northeast.

cleaning the concrete floor

Second Floor, Mid-floor (February 21, 2020)

Process of cleaning the concrete floor to remove dirt and dust before polishing the concrete.

cleaning the concrete floor

Second Floor, South Side (February 21, 2020)

View of the south side concrete floor where it had been cleaned.

cleaning the concrete floor

Second Floor, Southwest Corner (February 21, 2020)

View of the southeast corner where the concrete floor had been cleaned up to the study spaces. The process of installing new ductwork components and the priming of the drywall of this area prevented further floor cleaning into this corner.

construction in southwest corner

Second Floor, Southwest Corner (February 28, 2020)

Broad view of the construction process around the custodial closet extension.

construction in southwest corner

Second Floor, Southwest Corner (February 28, 2020)

Broad view of the construction process of the new study spaces. All drywall is primed and new ductwork placed. New support racks and conduits running across the ceiling for the new Ethernet upgrades.

construction on south side

Second Floor, South Side (February 28, 2020)

View of the construction process around the restrooms on the south side of the floor.

new ductwork

Second Floor, Southeast Corner (February 28, 2020)

Placement of new ductwork continues in the southeast corner.

priming drywall of drop ceiling accents

Second Floor, East Wall (February 28, 2020)

View of the drywall of the drop ceiling accents being primed for painting.

construction on south side

Second Floor, South Side (February 28, 2020)

Broad view of the construction process on the south side looking northwest.

construction on storage vault

Second Floor, Storage Vault (February 28, 2020)

Broad view of the construction process along the exterior walls of the storage vault and office space.

construction in northwest corner

Second Floor, Northwest Corner (February 28, 2020)

Broad view of the construction process outside the archive.

drywall installation

Second Floor, Reading Room (February 28, 2020)

Placement of drywall in the Reading Room (and the archive as a whole) almost completed.

masonry repairs

Second Floor, Sorting Room (February 28, 2020)

Masonry repairs conducted on the exterior wall of the Sorting Room. The repair work was to replace broken or missing masonry bricks along the top of the wall. To accomplish these repairs, the drywall was removed and the insulation was pulled away from the masonry wall.

masonry repairs

Second Floor, Storage Vault (February 28, 2020)

Masonry repairs conducted on the exterior wall of the Storage Vault. The repair work was to replace broken or missing masonry bricks along the top of the wall. To accomplish these repairs, the drywall was removed and the insulation was pulled away from the masonry wall.

removal of drop ceiling

Second Floor, North Hallway (February 28, 2020)

Removal of the entire drop ceiling from the north hallway.

painting drop ceiling accents

Second Floor, Mid-floor (April 3, 2020)

Drop ceiling accents throughout the central part of the floor are being painted.

painting drop ceiling accents

Second Floor, Mid-floor (April 3, 2020)

Facing northwest, another vantage point of the drop ceiling accents being painted.

painting drop ceiling accents

Second Floor, West Wall (April 3, 2020)

Drop ceiling accents along the west wall being painted.

painting drop ceiling accents

Second Floor, Office Space (April 3, 2020)

Drop ceiling accents in front of the new office space being painted.

painting walls

Second Floor, Southwest Corner (April 3, 2020)

The walls of the new study spaces being painted.

painting walls

Second Floor, Southwest Corner (April 3, 2020)

The walls along the custodial closet being painted.

placing support wires for new ceiling

Second Floor, Southeast Corner (April 3, 2020)

Placement of the new support wires for the new drop down ceiling frame. Support wires are bolted into the concrete and spaced in a pattern to support the anticipated weight of the drop ceiling frame and tiles.

pipes for new sprinkler system

First Floor, Southeast Corner (April 9, 2020)

Placement of pipes for the new sprinkler system installation on the first floor.

pipes for new sprinkler system

First Floor, Northeast Corner (April 9, 2020)

Placement of pipes for the new sprinkler system installation on the first floor.

pipes for new sprinkler system

First Floor, Southwest Corner (April 9, 2020)

Placement of pipes for the new sprinkler system installation on the first floor.

pipes for new sprinkler system

First Floor, Southwest Corner (April 9, 2020)

Placement of parts and supplies for the new sprinkler system installation on the first floor. Due to the pandemic shutdown and closure of the library, this process was able to move forward more smoothly without placing restrictions on the construction workers. 

drilled hole through floor

First Floor, Southwest Corner (April 9, 2020)

Holes were drilled through the concrete floor so pipes could be placed connecting the basement up to the second floor. The larger hole will serve as the primary conduit of water throughout the system for each floor.

removal of ceiling tiles

First Floor, Southwest Corner Ceiling (April 9, 2020)

Removal of ceiling tiles for the placement of pipes throughout the floor.

sprinkler system pipes

Second Floor, Sprinkler System (April 10, 2020)

View of the sprinkler system pipes with conduit tubing to be connected to sprinkler heads.

electrical upgrades

Second Floor, Electrical Work (April 10, 2020)

View of the supports for the new electrical conduits.

painting drop ceiling accents

Second Floor, Mid-floor Ceiling (April 10, 2020)

Drop ceiling accents being painted with second color. 

painting walls

Back Stairwell (April 10, 2020)

The divider wall framing the back stairwell being painted (the entire length of the stairwell).

painting drop ceiling accents

Second Floor, Reading Room Ceiling (April 10, 2020)

Drop ceiling accents in the Archive's Reading Room being painted with second color.

painted ductwork

Second Floor, Storage Vault (April 10, 2020)

View of the vault ductwork being painted.

removal of ceiling tiles

Second Floor, Huddle Room Ceiling (April 10, 2020)

Removal of the ceiling tiles and old lighting in the Huddle Room.

placing support wires for new ceiling

Second Floor, Huddle Room Ceiling (April 24, 2020)

With the old ceiling removed, new support wires for the new drop down ceiling placed.

placing support wires for new ceiling

Second Floor, Group Study Room #1 Ceiling (April 24, 2020)

With the old ceiling removed, new support wires for the new drop down ceiling placed.

pipes and supplies for sprinkler system

First Floor, Government Documents Area (April 24, 2020)

Placement of parts and supplies for the new sprinkler system installation on the first floor.

First Floor, Southwest Corner (April 24, 2020)

View of pipe fittings and other equipment for the sprinkler system installation project.

sprinkler system pipes

First floor, South Wall (April 24, 2020)

Placement of new pipes along the south wall and a support structure running vertically for the pipes connecting all the floors.

sprinkler system pipes

First Floor, Public PC Area (April 24, 2020)

Box of conduit tubing for connecting the pipes to sprinkler heads.

sprinkler system pipes

First Floor, Reference Area (April 24, 2020)

Placement of new pipes above the Reference Collection extending to the emergency exit and the restrooms on the north side of the first floor.

sprinkler system pipes

First Floor, North Restrooms Area (April 24, 2020)

Placement of new pipes in front of the restrooms on the north side.

sprinkler system pipes

First Floor, Director's Office (April 24, 2020)

Placement of new pipes outside the office of the library director.

sprinkler system pipes

Instruction Room Ceiling (April 24, 2020)

Placement of new pipes along the west wall of the Instruction Room.

sprinkler system panel

New Pull Alarm & Sprinkler System Panel (April 24, 2020)

As a part of the new sprinkler system, a system panel and a pull alarm panel was placed near the front entrance.

fire alarm strobes

Fire Alarm Strobes (April 24, 2020)

Throughout the building, new fire alarm strobe lights with audio alerts placed on the ceiling.

drop ceiling grid

Second Floor, Southwest Corner (April 24, 2020)

Placement of the new drop ceiling grid.

drop ceiling grid

Second Floor, Sorting Room (April 24, 2020)

Placement of the new drop ceiling grid.

drop ceiling grid

Second Floor, Reading Room (April 24, 2020)

Placement of the new drop ceiling grid.

light fixtures

Second Floor, Reading Room (April 24, 2020)

Placement of new LED lighting in the drop ceiling grid and recessed lighting fixtures on the ceiling accents.

light fixtures

Second Floor, North Hallway (April 24, 2020)

Placement of new drop ceiling grid with new LED lighting.

light fixtures

Second Floor, North Side (April 24, 2020)

Placement of new drop ceiling grid with new LED lighting. 

light fixtures

Second Floor, Exterior of Archive (April 24, 2020)

Placement of new drop ceiling grid with new LED lighting.

light fixtures

Second Floor, Mid-floor (April 24, 2020)

Placement of new drop ceiling grid with new LED lighting.

light fixtures

Second Floor, East Wall (April 24, 2020)

Placement of new drop ceiling grid with new LED lighting.

light fixtures

Second Floor, Southeast Corner (April 24, 2020)

Placement of new drop ceiling grid with new LED lighting.

light fixtures

Second Floor, LED Light Boxes (April 24, 2020)

Placement of two large LED light boxes. This design element was replicating the atrium element of the original library (now the Art Building).

column

Second Floor, Column Design (April 24, 2020)

The existing columns were updated with design accents and wood trim. Pictured here is the top of the column. Each column was framed with a ceiling accent and a dark, wood trim was added to the top creating an ornamental aesthetic that was missing from this architectural elements.

sprinkler system pipes

First Floor, Director's Office (May 5, 2020)

Work on the new sprinkler system continues from outside the Director's Office to the News Room.

sprinkler system pipes

First Floor, Director's Office (May 5, 2020)

Work on the new sprinkler system continues from outside the Director's Office to throughout the Periodical Collection area.

painting stairwells

North Stairwell (May 5, 2020)

Before repainting the north and south stairwells, old, flaky paint was scrapped off the walls, ceiling and guardrails.

painting stairwells

South Stairwell (May 5, 2020)

Placing paper guards to minimize paint spills on stair steps. View of second floor doorway from stairwell landing.

painting stairwells

South Stairwell (May 5, 2020)

Placing paper guards to minimize paint spills on stair steps. View of first floor doorway from stairwell landing.

light fixtures

Second Floor, Storage Vault (May 5, 2020)

Finished placing and painting the new ductwork. New LED lighting installed. 

tracks for glass wall

Second Floor, Sorting Room (May 5, 2020)

New LED lighting installed. New ceiling tiles are being placed. Metal tracks being placed for the glass wall installation.

new wood cabinets

Second Floor, Reading Room (May 5, 2020)

Placement of new wood cabinets with adjustable shelves.

tracks for glass wall

Second Floor, Reading Room (May 5, 2020)

Metal tracks being placed along the floor for the glass wall.

light fixtures

Second Floor, Group Study Room #1 Ceiling (May 5, 2020)

New drop ceiling grid and LED lights installed. Placing new ceiling tiles.

light fixtures

Second Floor, Huddle Room Ceiling (May 5, 2020)

New drop ceiling grid and LED lights installed. Placing new ceiling tiles.

new ceiling tiles

Second Floor, Southeast Corner (May 5, 2020)

Looking north, new drop ceiling grid and LED lights installed. Placing new ceiling tiles.

light fixtures

Second Floor, LED Light Boxes (May 5, 2020)

New LED light box installed. Placing new ceiling tiles around the edge of the light box.

light fixtures

Second Floor, LED Light Boxes (May 5, 2020)

View of both finished light boxes. Placement of new ceiling tiles throughout the south side of the floor.

light fixtures

Second Floor, LED Light Boxes (May 5, 2020)

View of finished light boxes and placement of new ceiling tiles at mid-floor.

new ceiling tiles

Second Floor, Mid-floor (May 5, 2020)

Looking southwest, placement of new tiles next to ceiling accents.

construction facing southwest

Second Floor, Overview of Construction (May 5, 2020)

A wide-view of the construction process.

wood accents on columns

Second Floor, West Wall (May 14, 2020)

Placement of wood trim panels on columns. 

wood accents on columns

Second Floor, East Wall (May 14, 2020)

Placement of wood trim panels on columns.

tracks for glass wall

Second Floor, Conference Room (May 14, 2020)

Metal tracks being placed along the floor for the glass wall.

tracks for glass wall

Second Floor, Southwest Corner (May 14, 2020)

Metal tracks being placed for the glass walls of the new study rooms. Some glass walls being put into position.

sprinkler system pipes

Basement, Auditorium (June 1, 2020)

Placement of new pipes along the south wall and across the seating area of the auditorium.

sprinkler system pipes

Basement, Systems Office (June 1, 2020)

Placement of new sprinkler pipes in the Systems Office.

sprinkler system pipes

Basement, Hallway Facing the Auditorium (June 1, 2020)

Placement of new pipes along the south side of the hallway.

sprinkler system pipes

Basement, Hallway Outside Writing Center (June 1, 2020)

View of new sprinkler pipes and new wiring outside the Writing Center door.

sprinkler system pipes

Basement, Hallway Facing Media Studio (June 1, 2020)

View of new sprinkler pipes and new wiring along south side of the hallway.

sprinkler system pipes

Basement, Media Studio (June 1, 2020)

Placement of new sprinkler pipes in the Media Studio.

sprinkler system pipes

Basement, Boiler Room (June 1, 2020)

View of new sprinkler pipes being routed through the wall of the Boiler Room.

sprinkler system pipes

Basement, Mechanical Room (June 1, 2020)

With the installation, a new master sprinkler system panel was placed on the wall.

sprinkler system pipes

Basement, Mechanical Room (June 1, 2020)

As part of the installation process, stored furniture and shelving had to be re-positioned to allow for placement of pipes and electrical conduit along the exterior wall. The stored furniture in this picture was removed from the second floor.

equipment and tools

Basement, Loading Dock Area filled with equipment and tools (June 1, 2020)

Among tools and stored furniture, equipment in the loading dock area continued to be utilized for the construction process.

clearing stairwell

Second Floor, Back Stairwell (June 01, 2020)

With the removal of the plyboard cover and tools, the back stairwell was reopened for use.

glass walls for study spaces

Second Floor, Study Spaces (June 1, 2020)

Placement of the glass walls for the new study spaces in the southwest corner.

glass walls for conference room

Second Floor, Conference Room (June 1, 2020)

Placement of the glass walls for the new conference room.

wood accents on columns

Second Floor, Mid-floor (June 1, 2020)

View of the construction process:  cleaning the floors, finishing wood trim placement on the columns with new electrical outlets at their base, and placement of the majority of ceiling tiles.

glass wall for office space

Second Floor, Office Space (June 1, 2020)

Placement of glass wall for the new office space.

glass walls for reading room

Second Floor, Reading Room (June 1, 2020)

Placement of the glass walls for the new reading room of the archive.

glass walls for reading room

Second Floor, Entrance to the Archive (June 1, 2020)

View of the entrance to the new archive, the reading room and the sorting room.

glass wall for sorting room

Second Floor, Sorting Room (June 1, 2020)

Placement of the glass (half) wall and the glass door to the sorting room. 

glass wall for sorting room

Second Floor, Sorting Room (June 1, 2020)

View from the opposite side, the glass (half) wall looking into the reading room area.

new wood cabinets

Second Floor, Sorting Room (June 1, 2020)

Placement of large storage cabinets along the north wall and regular cabinets along the west wall of the sorting room.

custodial closet

Second Floor, Custodial Closet Add-on (June 12, 2020)

View of the finished add-on to the custodial closet to house their large equipment.

custodial closet

Second Floor, Custodial Closet (June 12, 2020)

View of the new electrical box and conduits for the second floor renovation.

utility closet

Second Floor, Utility Closet (June 12, 2020)

View of the new utility closet housing the new Ethernet rack and main water pipe with gauge value for the second floor sprinkler system.

new ceiling

Second Floor, Group Study Room #1 (June 12, 2020)

Finished placement of the new ceiling in Group Study Room #1.

new ceiling

Second Floor, Huddle Room (June 12, 2020)

Finished placement of the new ceiling in the Huddle Room.

new ceiling

Second Floor, Study Spaces (June 12, 2020)

Finished placement of the new ceiling and glass walls of the new study spaces (southwest corner of the second floor).

new ceiling

Second Floor, Southwest Corner (June 12, 2020)

Finished placement of the new ceiling in the southwest corner of the second floor.

new ceiling

Second Floor, Southeast Corner (June 12, 2020)

Finished placement of the new ceiling and wood trim on columns in the southeast corner of the second floor.

new ceiling

Second Floor, East Wall (June 12, 2020)

Finished placement of the new ceiling and wood trim on the columns on the east side of the second floor.

new ceiling

Second Floor, Mid-floor (June 12, 2020)

Finished placement of the new ceiling and wood trim on the columns around the back stairwell.

new ceiling

Second Floor, North Side (June 12, 2020)

Finished placement of the new ceiling and wood trim on the north side of the second floor.

new ceiling

Second Floor, Office Space and Exterior of Archive (June 12, 2020)

Finished placement of the new ceiling and wood trim next to the new office and exterior of the archive.

frame for signage cutout

Second Floor, Exterior of Archive (June 12, 2020)

Placement of wood frame in wall cutout for archive signage. Taped on the wall are design layout for this signage.

glass walls for reading room

Second Floor, Exterior of Archive (June 12, 2020)

Completed the glass wall installation for the exterior of the Reading Room.

new ceiling

Second Floor, Reading Room (June 12, 2020)

Finished placement of the new ceiling for the Reading Room.

wood cabinets

Second Floor, Sorting Room (June 12, 2020)

Construction of wood cabinets and work counter along the half-wall.

wood cabinets

Second Floor, Sorting Room (June 12, 2020)

Construction wood cabinet and counter island in the center of the Sorting Room.

staining old wood

Second Floor, Instruction Room (June 12, 2020)

The existing wood door and threshold were re-stained a darker color to match the new wood trim elements installed on the columns and in the archive.

staining old wood

Second Floor, East Wall (June 12, 2020)

The existing wood walls of the front atrium were re-stained to match the new wood trim elements installed on the columns.

sprinkler system pipes

First Floor, Southwest Corner (June 23, 2020)

View of the main water pipe with gauge value for the first floor sprinkler system.

new water line

Southwest of Building, Behind Burton House (June 23, 2020)

View from the Library's loading dock ramp looking southwest. Construction to place new water pipe underground (behind the Burton House) from the city's water line along College Avenue to the Library (southwest corner of the building).

demolition of sidewalk

Demolition of Sidewalk (June 23, 2020)

Using heavy equipment, the sidewalk along the loading dock ramp was demolished in order to run new water pipes to the Library's new sprinkler system.

demolition of sidewalk

Demolition of Sidewalk (June 23, 2020)

View of the entire length of sidewalk removed on the southwest corner of the building.

digging trench

Digging Trench for New Water Pipes (June 24, 2020)

Heavy equipment digs a trench across the back parking lot area to connect a new water line up to the library. 

digging trench

Digging Trench for New Water Pipes (June 24, 2020)

View of the debris pile as asphalt and dirt are removed to create a trench across the parking lot for laying new pipes up to the library.

digging trench

Placing New Water Lines to Building (June 29, 2020)

After completing the trench, more dirt was removed from the sidewalk area allowing the new water line to be placed next to the building.

polished floor

Second Floor, Concrete Floors (June 30, 2020)

With most of the renovation work complete and the floor being clean, the concrete surface was polished.

cleaning the glass walls

Second Floor, Study Spaces (June 30, 2020)

With most of the renovation work complete, the glass walls of the new study spaces were professionally cleaned.

metal trim on columns

Second Floor, Southeast Corner (June 30, 2020)

With most of the renovation work complete, metal trim edges were placed on the columns.

cleaning the glass walls

Second Floor, Office Space (June 30, 2020)

With most of the renovation work complete, the glass wall of the new office space was professionally cleaned.

storage room

Second Floor, Storage Room (June 30, 2020)

View of the storage room next to the new office. 

vertical wood trim

Second Floor, Archive Entrance (June 30, 2020)

Placement of vertical wood elements next to the front entrance and the blue accent trim. These elements will help frame entrance signage to be placed on this wall.

renovation overview

Second Floor, Overview of Renovation (June 30, 2020)

A view of the renovation from the vantage point of the Archive's Reading Room.

glass cabinet doors

Second Floor, Reading Room (June 30, 2020)

Placement of glass doors on the wood cabinets.

glass cabinet doors

Second Floor, Sorting Room (June 30, 2020)

Placement of glass doors on the wood storage lockers.

tile back splash for water fountain

Second Floor, Water Fountains (June 30, 2020)

Placement of new tile back splash for the water fountain next to elevator. 

tile back splash for water fountain

Second Floor, Water Fountains (June 30, 2020)

Placement of new tile back splash for the water fountain in the north hallway.

digging trench

Placing New Water Lines to Building (July 6, 2020)

After removing additional dirt from the sidewalk area, the new water pipes are put into their final position.

buried water pipes

New Water Lines Buried (July 14, 2020)

New water lines placed up to the building and buried under dirt.

pipes for new sprinkler system

Basement, Mechanical Room (July 14, 2020)

Placement of new main pipe connecting outside water lines buried under dirt (sidewalk) to the library's sprinkler system.

new water line

Basement, Mechanical Room (July 14, 2020)

Placement of new main pipe connecting outside water lines to the library's sprinkler system.

pipes for new sprinkler system

Basement, Mechanical Room (July 14, 2020)

Placement of new pipes connecting the main water pipes on the first and second floor and the sprinkler system throughout the basement floor.

tile placement around floor ventilation

Second Floor, East Wall (July 14, 2020)

Placement of tile on the elevated floor surface around a series of floor ventilation ducts along the east wall.

new water fountain

Second Floor, ADA compliant water fountain (July 14, 2020)

A new water fountain was installed near the elevator to address wheelchair accessibility.

new counter tops

Second Floor, Reading Room (July 14, 2020)

New white counter tops placed on top of the waist-high wood cabinets. Installation of the glass cabinet doors completed.

new counter tops

Second Floor, Sorting Room (July 14, 2020)

New white counter top placed for the staff workspace.

new counter tops

Second Floor, Sorting Room (July 14, 2020)

New white counter tops placed on the cabinet island and waist-high cabinets along the west wall. Installation of the glass cabinet doors completed.

high density shelving

Second Floor, Reading Room (July 14, 2020)

Shelf ends and metal pieces delivered for the new high density shelving.

high density shelving

Second Floor, Reading Room (July 14, 2020)

Shelf wheels delivered for the new high density shelves.

high density shelving

Second Floor, Sorting Room (July 14, 2020)

Shelf wheels and shelves delivered for the new high density shelving.

high density shelving tracks

Second Floor, Storage Vault (July 14, 2020)

Placement of the gliding tracks for the shelf wheels. View of the new tile floor for the storage vault room.

high density shelving

Second Floor, Storage Vault (July 14, 2020)

Shelves and vertical support pieces delivered for the new high density shelves.

sprinkler system pipes

Basement, Mechanical Room (July 20, 2020)

Completion of the pipe installation for the library's sprinkler system.

exterior pipe seal

Water Line Installation (July 20, 2020)

Completion of the water line installation project. A pipe seal added and a new fire hydrant placed nearby.

water fountain

Second Floor, Water Fountains (July 20, 2020)

In the north hallway, the water fountain was restored back into its previous location.

tile placement around floor ventilation

Second Floor, East Wall (July 20, 2020)

Installation of the new tile along the east wall completed.

tile placement around floor ventilation

Second Floor, New Floor Tile (July 20, 2020)

A closer view of the new tile installed along the east wall.

power bars added

Second Floor, Study Spaces (July 20, 2020)

Installation of a power bar along the outer wall of the new large group study space.

power bars added

Second Floor, Study Spaces (July 20, 2020)

Installation of a power bar along the outer wall of the new conference room space.

power bars added

Second Floor, Study Spaces (July 20, 2020)

Installation of a power bar along the outer wall of one of the small study spaces.

new door

Second Floor, Custodial Closet (July 20, 2020)

Installation of new door to the custodial closet.

new door

Second Floor, Storage Vault (July 20, 2020)

Installation of new doors to the storage vault.

hvac control panel

Second Floor, Storage Vault (July 20, 2020)

Installation of new control panel for the new HVAC system for the vault. For clarification, the climate controls for this room operate independently from the rest of the library building.

high density shelving

Second Floor, Storage Vault (July 20, 2020)

Installation of the high density shelving completed. These shelves will house the archival collections donated by General Tom Stafford. 

high density shelving

Second Floor, Storage Vault (July 20, 2020)

View of the central aisle of the high density shelving. This shelving is unique because it only has one usable aisle between shelves to access the materials.

high density shelving

Second Floor, Storage Vault (July 20, 2020)

View of the length of the room through the shelves.

high density shelving

Second Floor, Storage Vault (July 20, 2020)

View of the entrance to the storage vault. The wheel cranks allow the shelves to be moved across the room with ease to gain access to the collection at any position of this room. These cranks include a locking mechanism to keep the shelves from moving while trying to pull materials from the shelf.

new carpet

Second Floor, Exterior of Archive (August 12, 2020)

Installation of new carpet for the seating area outside the archive into the archive's reading room. Also, the wall cutout is painted in preparation for the archive signage.

book shelves

Second Floor, North Side (August 12, 2020)

While waiting for the state Fire Marshall inspection, the library movers return to assemble shelving for the eventual return of the library's book collection.

book shelves

Second Floor, North Side (August 12, 2020)

View of how the library movers measured and staged the book shelf arrangement.

new carpet

Second Floor, Northeast Seating Area (August 14, 2020)

Installation of new carpet for the northeast seating area (facing the clock tower).

new carpet

Second Floor, Center Seating Aisle (August 14, 2020)

Installation of new carpet outlining a new seating area aligned with the back stairwell for an easy exit from the second floor.

new carpet

Second Floor, Southeast Seating Area (August 14, 2020)

Installation of new carpet for the southeast seating area (facing the clock tower).

new carpet

Second Floor, Southeast Corner (August 14, 2020)

Installation of new carpet for the new seating area in the southeast corner.

new door

Second Floor, South Side Restrooms (August 14, 2020)

Installation of new doors for the second floor restrooms.

new carpet

Second Floor, Study Spaces (August 14, 2020)

Installation of new carpet for the new study spaces and the seating area adjacent to these rooms.

new carpet

Second Floor, Office Space (August 14, 2020)

Installation of new carpet for the new office space.

metal trim on wood accents

Second Floor, Entrance to the Archive (August 14, 2020)

Application of metallic trim to the vertical wood accents at the entrance of the archive.

new carpet

Second Floor, Huddle Room (August 14, 2020)

Installation of new carpet for this study room.

new carpet

Second Floor, Group Study Room #1 (August 14, 2020)

Installation of new carpet for this study room.

poured concrete

Restoration of Sidewalk (August 14, 2020)

New concrete poured to restore the sidewalk along the loading dock ramp.

moving books

Second Floor, North Side (September 18, 2020)

Library movers begin moving books back into the library.

moving books

Second Floor, Moving Books (September 18, 2020)

Library movers arrange their carts in progression of the Dewey Decimal System before placing them on the shelf.

moving books

Second Floor, Shelving Book Collection (September 18, 2020)

First library books to be shelved back on the second floor. 

privacy filter

Second Floor, Study Spaces (September 18, 2020)

A privacy filter applied to all the study room glass walls.

moving books

Second Floor, Moving Books (September 24, 2020)

Library movers off loading more books at the loading dock and bringing them up the elevator.

moving books

Second Floor, Moving Books (September 24, 2020)

At this stage of returning books to the second floor, more shelving is erected to allow the moving process to proceed smoothly without delays.

wall artwork

Second Floor, Entrance to the Archive (September 24, 2020)

Installation of artwork on the wall next to the archive's entrance. A photograph of General Stafford with metal letters mounted to the wall.

wall artwork

Second Floor, Exterior of Archive (September 24, 2020)

Installation of artwork on the exterior wall of the archive. A photograph of the Earth from the Moon with black, glossy letters mounted to the wall. The letters emphasize a quote attributed to General Stafford. 

library tables

Second Floor, Study Spaces (November 12, 2020)

Placing library tables into new study space rooms and adjacent seating area.

conference table

Second Floor, Conference Room (November 12, 2020)

Saved from the Southwestern Room, this wood table was added to the new conference room.

computer standing desk

Second Floor, North Side (November 12, 2020).

New restroom signs mounted to the wall. The computer standing desk returns to its original position outside the Instruction Room. This desk holds three computers for quick searching of the library's holdings.

room number sign

Second Floor, Entrance to the Archive (November 12, 2020)

Placement of a room number sign for the archive's Reading Room.

archive doors

Second Floor, Entrance to the Archive (November 12, 2020)

Delivery of the archive's front doors after being stained off-site.

cabinet lighting

Second Floor, Reading Room (November 12, 2020)

Installation of LED lighting to each cabinet compartment which is tied to the overhead lighting for the room.

room number sign

Second Floor, Sorting Room (November 12, 2020)

Placement of a room number sign for the archive's Sorting Room.

room number sign

Second Floor, Storage Vault (November 12, 2020)

Placement of a room number sign for the archive's Storage Vault.

artwork removal

Second Floor, Entrance to the Archive (November 12, 2020)

Removal of wall artwork and mounted letters due to faulty installation.

artwork removal

Second Floor, Exterior of Archive (November 12, 2020)

Removal of wall artwork and mounted letters due to faulty installation. LED lighting added to the wall cutout creating a dramatic effect for the signage to be placed in this location.

library chairs

Second Floor, Study Spaces (December 3, 2020)

Placing library chairs into new study space rooms and adjacent seating area.

task chairs

Second Floor, Conference Room (December 3, 2020)

Retained from the Southwestern Room, these task chairs were added around the wood conference table.

library collection

Second Floor, West Wall (December 3, 2020)

View of the west wall with the entire book collection returned to the second floor.

library table and chairs

Second Floor, Back Stairwell (December 3, 2020)

Behind the back stairwell, a secluded seating area was created.